top of page
Background Only.png
SW Regional Conference Logo

Transportation & Aviation

De Soto Progressive Design Build - Another Tool in the Alternative Delivery Toolbox

May 3, 2024

Breakout Session 3

2:20 PM

Breakout Rooms

1 DBIA Credit Hour, 1 AIA LU

In the City of De Soto, Kansas, just southwest of the City’s primary residential and commercial districts, the former Sunflower Army Ammunition Plant is being transformed into Astra Enterprise Park. This industrial park has over 9,000 acres available for a job’s hub for the region. Panasonic’s electric vehicle battery manufacturing facility, scheduled to open in Spring 2025, is the first building in the industrial park. At 14 square miles, if the park were a city, it would be the 16th largest in Kansas: larger than Pittsburg, Junction City, Emporia – and even De Soto.


This development has significantly impacted demand for the City’s infrastructure. To accommodate projected traffic, expected job influx, and growing population, De Soto needs to meet these demands on a very accelerated timeline. This includes significantly upgrading transportation, power, data/communication, drinking water, wastewater, and stormwater infrastructure to support municipal and industrial development.


The Kansas Department of Transportation (KDOT), in partnership with Clarkson Construction Company, HDR, Burns & McDonnell, and Garver, is administering the project to provide the transportation infrastructure needed to support the 300-acre Panasonic facility. This roadway expansion project required an extremely condensed schedule with just 6 months for public procurement, 6 months for design, and approximately 18 months for construction. Given the critical schedule drivers, the necessity for multiple utility relocations, and the requirement for extensive engagement with various third parties, a delivery approach that is both flexible and collaborative became imperative. This project will be KDOT’s first Progressive Design-Build (PDB) project.


The project includes updating about 4.5 miles of two-lane roadway to a new, divided four-lane concrete roadway with curb and gutter, three roundabouts, sidewalks, and lighting. The project also includes new, enclosed storm sewer systems; two, single-span bridges; and multiple reinforced concrete box structures. Multiple utilities had to be relocated, including water, sanitary sewer, gas, fiber optics, power transmission, and power distribution service.

The work will be along the existing footprint of 103rd Street between Evening Star Road and the Lexington Avenue/K-10 interchange. The same roadway improvements will take place on approximately one-half mile of Astra Parkway, formerly known as Main Avenue, running north-to-south along the new Panasonic facility. The project is on track to be substantially complete near the end of 2024.

LEARNING OBJECTIVES:

  1. Apply Progressive Design Build Strategies: Participants will be able to apply progressive design-build strategies to accommodate rapid infrastructure demands, as exemplified by the Astra Enterprise Park development case study.

  2. Utilize Risk Registers for Cost Control: Participants will be able to organize and use risk registers effectively to predict and limit cost escalations in large-scale projects.

  3. Extract Lessons from Expedited Procurement: Participants will be able to summarize and apply lessons learned from the expedited procurement process to streamline future project timelines.

  4. Tailor Progressive Design Build for Various Projects: Participants will be able to analyze project requirements to 'right-size' the progressive design-build approach for different scales and scopes of projects.

Sponsored by




0 DAYS TO THE EVENT
May 02, 2024, 7:00 AM CDT
Houston, TX
bottom of page